DEBRIEFING OF CHILL SETUP FOR WEEK 4/24-4/28:

CSU-CHILL Facility Progress Report #17: 4/24 - 28/2000

Radar set up at the ITR site was started this week.

Specific Activities:

  1. Radar assembly activities were started on Tuesday, 4/25 when the CP-2 radome tie-down ring sections were laid out on the new antenna foundation pad. The ring sections were cleaned with solvent and new foam air sealant material was applied. The fully assembled ring was anchored to the concrete by the paAd contractor on Thursday, 4/27.
  2. Herman Ready Mix also supplied a semi-truck tractor and driver to reposition the trailers. The MOCCA, CHILL user van, and the FPS-18 trailer were all positioned properly with respect to the pad center point. Connection of the various inter-trailer cables has been started.
  3. Commercial power became available at the site during the late morning hours of Friday, 4/28. The radome blowers have been test run to confirm that they are rotating in the correct direction. The electrical contractor also trenched in the phone lines to the radar vans. The phone company should connect these lines next week.
  4. Crane activities are scheduled to start on Monday, 5/1. A locally available 30 ton crane will arrive in the morning to set up the three pedestal extension tube sections. If the weather conditions look promising for Tuesday morning, the 70 ton crane required to finish the antenna and radome installation will leave its Ft. Morgan base for ITR around noon.


EQUIPMENT STATUS:

SYSTEM STATUS
Ops Center Installation underway
CHILL Installation underway
S-Pol Site preparation underway
LMA Some installation underway
MGLASS Not yet operational
T-28 Not yet operational
Storm ballooning Not yet operational
Mobile Mesonet Not yet operational
YRFS Operational
NWS Operational