CWB project work schedule
|
Task 1 |
Responsible person |
Detailed work |
Time by |
|
Retros Exp. |
H.-C. Lin CWB Y.-R. Guo (review the results) |
1, Re-set the experiments (15 Aug. to 15 Sep. 2003); |
15 May |
|
2, verification against Analysis (CWB or EC?) |
22 May |
||
|
3, verification against observations (Sound) |
31 May |
||
|
TC Bogus |
H.-C. Lin CWB |
1, TC bogus data generator (need document). |
31 Mar. |
|
2, Decoder program to LITTLE_R format (2003062912Z
data) |
8 April |
||
|
3, First guess field with Typhoon. |
? |
||
|
Y.-R. Guo CWB |
4, 3DVAR OBS preprocessor (Bogus FM-135). |
18 April |
|
|
5, 3D-Var Exp. With TC Bogus for Dujuan. |
15 May |
||
|
Global Bogus |
CWB H.-C. Lin |
1, Processing the Global bogus data (same period of
Retros. Exp) |
15 May |
|
2, 3D-Var cycling experiment parallel to Retros.
Exp. |
31 May |
||
|
3, Comparison with Retros. Exp without Global Bogus
data |
15 June |
||
|
BES create |
CWB H.-C. Lin |
1, Prepare the CWB NFS forecasts for Stage0 (
month). |
20 May |
|
2, Convert NFS variables to WRF control variables |
31 May |
||
|
Y.-R. Guo |
3, Solve the problem in conversion between (u,v) and
(y,c) |
15 May |
|
|
4, Separate the Stage0 from 3D-Var code. |
31 May |
||
|
CWB |
5, Generate the BES with NFS data |
15 June |
|
|
6, Inspection of the new BES and Single OBS test |
30 June |
|
Task 2 |
Responsible person |
Detailed work |
Time by |
|
GPS RO Observation error |
X. Ma (Consultant Y.-R. Guo,
Shu-Ya Chen) |
1, Get the GPS RO data from CDAAC (level2/wetPrf) |
4 May |
|
2, Modify the decoder program (consistent LITTLE_R
format) |
11 May |
||
|
3, Modify OBS preprocessor to consider the time-,
geographic- and altitude-dependent OBS error |
20 May |
||
|
GPS RO data quality control |
Y.-R. Guo |
1, Modify 3D-Var code to ingest the GPS RO data |
27 May |
|
2, Modify the innovation subroutine |
3 June |
||
|
X. Ma H.-C. Lin |
3, Implement the quality control procedure (Lidia
Cucurull) |
10 June |
|
|
4, Calculate the rejection rate of GPS RO data to
tune the quality control parameters |
24 June |
||
|
GPS RO observation operator
improvement |
Y.-R. Guo |
1, Consider the vertical variation of the perigee
points. |
10 June |
|
2, Improve the formulation of the refractivity index |
24 June |
||
|
X. Ma H.-C. Lin |
3, Assess the impact of the improvements |
15 July |
|
|
Typhoon Dujuan experiments |
CWB Y.-R. Guo H.-C. Lin X. Ma |
1, TC Bogus impact |
|
|
2, New NFS BES impact |
|
||
|
3, OBS error impact |
|
||
|
4, New operator impact |
|